1. Before installation, the construction unit should inspect the product qualification certificate, design documents, and pre assembly records of the components, and re check the dimensions of the components. When the deformation and defects of steel structures exceed the allowable deviation, they should be treated. Before installation, a detailed measurement and correction process should be prepared. For the welding of thick steel plates, a process test simulating the product structure should be conducted before welding and installation, and corresponding construction processes should be prepared. A certain degree of arching should be pre-set for the assembled roof truss.


2. After the steel structure is lifted into place, the control points of the component positioning axis, elevation and other design requirements should be measured and marked, and the quality of the lifting joint should be inspected before welding. Install temporary supports and steel cables to ensure the safety and stability of the steel roof truss during construction.


3. When installing steel structures, the construction unit shall submit the elevation dimensions, welding, painting, etc. of each component after lifting to the supervisor for acceptance.

 

Send Inquiry